FDC Revises Handover Schedule for 4,000 Flats
Photo: MV+
The Fahi Dhiriulhun Corporation (FDC) has issued a revised timetable for the completion and handover of 4,000 flats under the government’s housing programme.
FDC previously stated that it expected to complete handovers by the end of last month. FDC released an updated schedule along with the announcement that the handover dates has been revised. Under the updated schedule, the following handovers are planned:
December 2025
- Week 2: Udhares Towers 11, 12, 13, 15 and 16
- Week 5: Amaan Dhoadhi Towers 1, 2, 3, 4, 12, 13 and 14
January 2026
- Weeks 3, 4 and 5: Udhares Towers 1–10
- Weeks 2 and 5: Amaan Dhoadhi Towers 5–10, 15 and 16
The handover process officially began on 28 October, when the first set of keys was presented at a ceremony held at Tower 14 of Amaan Udhares. So far flats from only tower 14 of Amaan Udhares have been handed over to tenants who have paid their security deposits.
The development, contracted to two Indian firms, consists of two- and three-bedroom units. Two-bedroom flats are priced at MVR 7,000 per month, plus a MVR 1,000 maintenance fee and a MVR 15,000 security deposit. Three-bedroom units are rented at MVR 9,500 per month, with a MVR 1,500 maintenance fee and a MVR 25,000 deposit.
Sixteen towers under the Amaan Udhares scheme are being constructed by Kalpataru Projects International Limited (KPIL), while the remaining sixteen, known as Amaan Dhoadhi, are being developed by India’s National Buildings Construction Corporation (NBCC). By August both contractors had completed more than 80 percent of the project.
FDC had previously said that as soon as the utility installations are completed in the towers, the handover process of the towers will begin.