Gov’t Reports 9% Advancement on Thila-Male Bridge Project
Government announced today that significant progress has been made on the Thila-Male Bridge project, with 9% advancement achieved in the past six months alone.
Overall, 37.71% of the project has been completed, marking a significant milestone in its development.
https://x.com/naadu_mv/status/1792474639551414687
The anticipated Male-Vilimale connection is slated to become operational by the conclusion of December 2025, bringing enhanced connectivity to the region.
https://x.com/naadu_mv/status/1792489649816129730
Minister of Construction and Infrastructure, Dr. Abdulla Muththalib, disclosed in March that 35% of the Thilamale’ Bridge Project had been successfully completed.
Dr. Muththalib further detailed that the current completion status now stands at 35.53%, surpassing expectations and indicating progress ahead of schedule.
Highlighting specific achievements, Dr. Muththalib noted that 24% of the pre-casting work for the superstructure has been accomplished, exceeding projected advancement by 1.11%.