Asphalt paving on Ameenee Magu is set to commence this week following the scheduled completion of aggregate base course (ABC) compaction works today, as contractors move into the next phase of road restoration.
Road marking works are expected to begin next week, signalling the final stages of surfacing along the targeted section.
The updates follow the reopening of Segments 1 and 2 of Ameenee Magu to general traffic after Maldives Transport and Contracting Company (MTCC) completed repair and paving works around key points, including the four corners near the Voice of Maldives area.
The road restoration project, awarded to MTCC on June 15 by the Ministry of Housing, Infrastructure, and Urban Development, aims to fix severe road deterioration through subgrade preparation, base compaction, asphalt laying, and line marking.
With Segments 1 and 2 already fully cleared of debris and opened to the public, repair crews are transitioning along the road, including Segment 3 from Izzuddin Magu to Koarukendi Hingun, to further improve traffic flow across Malé.
ABC compaction works at Ameenee Magu are scheduled to be completed tomorrow, with asphalt works set to commence this week. Road marking works are expected to begin next week. #MTCCProjects #TeamMTCC #RayyithungeKunfuni #GaumuBinaakurumugaaMTCC https://t.co/oFiYSitPOa— MTCC Plc (@MTCCPlc) October 11, 2026