Hulhumale Phase 3 Land Reclamation Project

MV+ News Desk | January 4, 2026

Hulhumalé Phase 3 reclamation reaches 77.8 per cent completion, according to Maldives Airports Company Limited (MACL), marking steady progress in the major housing development project.

Photo: MV+

A total of 49 hectares have been reclaimed so far, with works continuing in line with the project’s approved timeline.

Photo: MACL

Reclamation resumed in November after delays caused by revisions to the Hulhumalé Master Plan, with the Housing Development Corporation overseeing the project.

Photo: MV+

Capital Marine and Civil Construction is carrying out the on-site works, following the project’s restart.

Photo: MV+

The project was temporarily suspended in 2023 after the Environmental Protection Agency halted works due to a mass coral bleaching event.

Photo: MV+
Photo: MV+

Works resumed in 2024 after EPA approval, allowing the project to continue under revised environmental conditions.

Photo: MV+

Hulhumalé Phase 3 is a key component of plans to address housing shortages in the Greater Malé region.

Photo: MV+

The reclaimed land will be developed into housing flats and residential areas, aimed at easing pressure from the region’s growing population.

    Photo: MV+